Major £30m BOXBAY facility works tender released at London Gateway
- constructnetuk
- 4 days ago
- 2 min read

A significant infrastructure opportunity has been released for the delivery of the BOXBAY automated high-bay container storage facility at London Gateway, with an estimated contract value of £30 million.
The project will be delivered within a live operational port environment and represents a major step forward in automated container storage infrastructure in the UK.
⸻
📦 Project overview
The scheme will deliver a large-scale automated storage structure with approximate dimensions of:
• 323m length
• 159m width
• 55m height
Designed to support high-density container storage, the facility will incorporate advanced structural, civil and building services systems.
⸻
🏗️ Scope of works
The contract covers a full design and build package, including:
Substructure & civils
• Removal of existing underground services
• Installation of 5,000+ precast piles (~28m deep)
• Construction of reinforced concrete raft foundation
• Stormwater drainage, utilities and service infrastructure
Superstructure
• Fabrication and erection of 15,000+ tonnes of structural steelwork
• Installation of ~50,000m² of cladding and 46,500m² roofing
• Construction of lift cores, staircases and rail systems for automated machinery
External & ancillary works
• Heavy-duty pavements and external civils
• Office/store building and transformer/e-house facilities
Building services
• Fire detection and prevention systems
• Power, lighting and IT infrastructure
• Ventilation, insulation and lightning protection
⸻
📍 Programme & procurement
• Location: Thurrock (UKH32)
• Contract value: £30m
• Duration: July 2026 – July 2028
• Procurement route: Competitive flexible procedure (utilities)
The process will begin with a Request for Information (RFI) stage, followed by a multi-stage tender process including potential negotiation rounds and a final Best and Final Offer (BAFO) submission.
⸻
⚠️ Key deadline
• Deadline for requests to participate: 29 April 2026
⸻
🚧 What this means for contractors
This is a major industrial and infrastructure project with significant packages likely across:
• Structural steel and fabrication
• Civils and groundworks
• M&E and building services
• Specialist infrastructure and automation interfaces
Given the scale and complexity, early engagement will be critical for contractors and supply chain partners looking to secure involvement.
⸻
📊 Early positioning opportunity
With the procurement at RFI stage:
👉 Shortlisting will happen early
👉 Supply chain strategies will be formed quickly
👉 Key delivery partners will be identified ahead of full tender
This is the stage where proactive contractors can get ahead of the competition.