top of page

£29.6m design & build opportunity launched under two-stage procurement process in Bedfordshire & Hertfordshire


A major construction opportunity has been released for contractors across the UK, with an estimated value of £29.64 million (inc. VAT) under a competitive two-stage design and build procurement route.


The scheme covers works across the Bedfordshire and Hertfordshire regions and is being delivered through a competitive flexible procedure, combining a pre-construction services phase followed by a full construction contract award.


🏗️ What is being procured?


The project involves the appointment of a contractor to deliver:


  • Contractor design services

  • Pre-construction design development

  • Construction methodology development

  • Full construction delivery following design approval


The successful bidder will first be appointed under a Pre-Construction Services Agreement (PCSA) before progressing to the main works contract.


📊 Contract overview


  • Estimated value: £24.7m – £29.64m

  • Contract type: Works (Design & Build)

  • Procurement route: Competitive flexible two-stage procedure

  • Contract duration: August 2026 – March 2029

  • Award date (estimated): 20 July 2026


📅 Key tender deadline


⏳ Stage 1 submission deadline: 27 April 2026, 12:00pm


All submissions must be completed via the dedicated e-sourcing portal:

👉 SourceDogg procurement platform


🧠 Stage 1 evaluation criteria


Stage 1 (PQQ) carries a 100% technical weighting, assessing:


  • Programme management & delivery capacity

  • Team structure & relevant experience

  • Health, safety & wellbeing

  • Innovation and environmental approach

  • Overall technical capability


Only the highest scoring bidders will progress to Stage 2, where commercial submissions will also be evaluated to determine the Most Advantageous Tender (MAT).



🎯 Why this opportunity matters


This is a high-value, long-term design & build opportunity, offering contractors the chance to:


  • Secure a multi-year pipeline (2026–2029)

  • Enter early through pre-construction involvement

  • Influence design development before full delivery stage

  • Compete under a structured two-stage procurement model


The inclusion of a PCSA phase makes this particularly attractive for contractors looking to shape the scheme early and reduce delivery risk before main works appointment.


 
 
bottom of page